United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Wednesday, August 08, 2007
From:
James Augustyn/Brian Schlieger, On-Scene Coordinator

To:
Jason El-Zein, ERB 1/RS-1
David Chung, OSWER
Al Taylor, MDEQ
Cheryl Howe, MDEQ
Rick Karl, USEPA
Mark Johnson, U.S. EPA R5
Bill Bolen, ERB 1
Mike Chezik, DOI
Jeff Cahn, USEPA

Subject: 

Initial POLREP
Tittabawassee River Reach J/K
Midland, MI
Latitude: 43.5719
Longitude: -84.2006


POLREP No.:
1
Site #:
B5KF
Reporting Period:
August 6-9, 2007
D.O. #:
Start Date:
8/6/2007
Response Authority:
CERCLA
Mob Date:
8/6/2007
Response Type:
Time-Critical
Completion Date:
NPL Status:
NPL
CERCLIS ID #:
MID980994354
Incident Category:
Removal Action
RCRIS ID #:
Contract #

Site Description

On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow) to negotiate an Administrative Order on Consent, to address removal of extremely elevated levels of dioxin-contaminated soil from an eroding river bank within Reach JK of the Tittabawassee River near Midland, Michigan.  Dow agreed to the terms of the Order and on July 12, 2007, the Order was signed by the Regional Administrator and Dow.  For additional background information please see the site profile.


Current Activities

On August 6, 2007, the removal action at the Reach JK site was initiated by Dow pursuant to the Administrative Order on Consent (AOC).

Dow’s contractor began clearing vegetation and establishing a temporary road into the area.  Reach JK will be divided into two areas.  The area along the river bank where contaminated soil will be excavated will be designated JK-1, and an area further back from the river bank where clean soil will be used to cap contaminated soil will be designated JK-2.

Dow’s contractor completed clearing vegetation through an area where an 8 foot fence will be installed surrounding a Riparian Forested Wetland within Reach JK-2

On-Scene Coordinator (OSC) Jim Augustyn provided oversight with assistance from U.S. EPA’s START Contractor, Weston Solutions, Inc.

The following tasks have been completed by Dow's contractor during the period from August 6-9, 2007:

•    Site survey to delineate area boundaries.
•    A temporary access road into the site excavation area has been established.
•    Vegetation and tree removal in section JK-2 of the site.

The following tasks are currently on going:  

•    Vegetation and tree removal along the river bank in order to access the excavation area of JK-1.  
•    Installation of erosion control silt fencing throughout the site.
•    Installation of silt curtain in the river along the shoreline.  


Planned Removal Actions

Dow's contractor will continue to remove vegetation, trees, and stumps along the river prior to excavating contaminated soil.

An 8 foot-high fence will be installed surrounding a Riparian Forested Wetland within Reach JK-2.

Excavated contaminate soil will be disposed of at Dow’s Salzburg Road Landfill


Key Issues

Review and approval of the Project Work Plan and associated Site-Specific Health and Safety Plan by U.S. EPA is pending.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


epaosc.net/TittabawasseeReachJK